Steps

  • Define stop categories: breakdown, changeover, material shortage, waiting, break
  • Log the duration and cause of every stop, automatically wherever the machine gives a signal
  • Distinguish planned from unplanned downtime
  • Analyse the top causes with a Pareto: tackle the biggest one first

Worked example (illustrative)

In one week there are 300 minutes of downtime:

  • 40% breakdown line 2 · 25% changeover · 20% material · 15% other
  • Pareto points to breakdown line 2 as the first target

Without it becoming extra work

Keeping records by hand grinds to a halt: it is half right and it comes too late. The stops are therefore read automatically from the machine signal; the operator only picks the cause. For the maintenance department this means downtime becomes demonstrable, ammunition to defend a maintenance budget, without the recording becoming a new job. The data stays in your own environment. VDS supplies the measurement; the solving stays with you.

Frequently asked questions

What is the difference between planned and unplanned downtime?

Planned downtime is foreseen (a break, a scheduled changeover); unplanned downtime is unwanted (a breakdown, a material shortage) and weighs more heavily in your availability.

How do you record downtime automatically?

By reading the machine's start/stop signal; the duration is determined automatically and the operator attaches a cause to it.

What is a Pareto analysis of downtime?

A ranking of stop causes from large to small, so that you find the few causes that account for most of the loss.

JW
Johannes WibbensHead of Operations · VDS Automation